City of CheyenneWyoming Department of TransportationFederal Highway Administration

High Plains Road Extension Project
Draft Environmental AssessmentVirtual Public Information Forum

Project Milestone Schedule

The milestone schedule below reflects key dates in the National Environmental Policy Act (NEPA) process. Exact dates are subject to change.

Project milestone schedule with dates for the High Plains Road Extension Project NEPA process
MilestoneDate/Time
Public Scoping PeriodJanuary 7 through February 4, 2026
Public Scoping Open HouseJanuary 29, 2026
Preliminary Draft EAMay 2026
WYDOT/FHWA ReviewLate April/Early May 2026
Public Release of Draft EAMay 2026
Public Comment PeriodJune 2026
Final EAEarly August 2026
FONSILate August 2026